Raise the Roof Agenda

Day 1

Essential Main Sequence:

 

Simultaneous Odd Jobs:

  • String across deck w/2x4 blocks (to address any truss problems)

 

  • Sweep the deck
  • Erect exterior wall partitions
  •  

    • Insulate the tub/shower wall
  • Start building rakes
  •  

    • Foundation back filling (if necessary)
  • Start building small trusses
  •  

    • Carry and distribute wall sheathing (from pile to wall location)
  • Erect interior wall partitions
  •  

    • Install #16 nail holders at block under studs for exterior sheathing
  • 2x8 double porch beams installed
  •  

    • Quality controlled exterior wall nailing
  • String and straighten long walls
  •  

    • Mark all door jambs for size and swing
  • Start exterior wall sheathing
  •  

    • Cut bottom plates of doors and closet
  • Install top plates on exterior and interior walls
  •  

    • Build attic saddles for plywood deck
  • Critical marking for trusses on top plates (no truss over plumbing wall; watch attic stairs & fan spacing)
  •  

    • Make sheathing 'A' frame lifting device
  • String across top plates and center partition, anticipate trusses
  •  

    • Storage room sheathing using OSB
  • Prepare trusses for first truss (exterior & interior)
  •  

     

    • Mark 1x3 on 24" centers for truss ties

     

     

    • Prepare & install pic board & braces

     

     

    • First truss up and braced from inside

     

     

    • Start gable end sheathing

     

     

     

    Day 2

    Essential Main Sequence:

     

    Simultaneous Odd Jobs:

    • Common trusses lifted up onto plates via ladders, or over the side

    • Brace front door entry wall to trusses
  • Common truss erection starts and proceeds non-stop
  •  

    • Chalk lines snapping 24" centers for roof (rough side up)
  • Small truss (porch offset) erection must have continous alignment or plumb cut ends
  •  

    • Install attic floor 3/4" plywood
  • Last gable end truss up & braced
    • Hand up roof sheathing to roof crew
  • Front/rear and porch rakes up
  •  

    • Fasten truss hurricane ties with Simpson nails
  • Gutter boards up both sides (caution: demo proper height via small blocks
  •  

    • Truss internal "X" bracing
  • Start roof deck sheathing; bottom course snap chalk lines both sides
  •  

    • Check all framing from plans (wall alignment, window sizes, corners drywall blocking)
  • Cut & fit roof sheathing stagger joints
  •  

    • Remove all internal bracing & nails
  • Install roof safety planks (long 2x4's) Caution all crews about sawdust roof
  •  

    • Homeowner kick walls for quality control on sheathing
  • Ensure 2" wide ridge gap at peak for birdbox building; see diagram
  •  

    • Metal drip edge installed

     

     

    • Gather debris into piles & bags or trailer; all useful materials stored; nail up door coverings and load trucks with ladders and tools