Essential
Main Sequence:
|
|
Simultaneous
Odd Jobs:
|
- String across
deck w/2x4 blocks (to address any truss problems)
|
|
|
|
Erect exterior
wall partitions
|
|
- Insulate
the tub/shower wall
|
|
Start building
rakes
|
|
- Foundation
back filling (if necessary)
|
|
Start building
small trusses
|
|
- Carry and
distribute wall sheathing (from pile to wall location)
|
|
Erect interior
wall partitions
|
|
- Install
#16 nail holders at block under studs for exterior sheathing
|
|
2x8 double
porch beams installed
|
|
- Quality
controlled exterior wall nailing
|
|
String and
straighten long walls
|
|
- Mark all
door jambs for size and swing
|
|
Start exterior
wall sheathing
|
|
- Cut bottom
plates of doors and closet
|
|
Install top
plates on exterior and interior walls
|
|
- Build attic
saddles for plywood deck
|
|
Critical marking
for trusses on top plates (no truss over plumbing wall; watch attic stairs
& fan spacing)
|
|
- Make sheathing
'A' frame lifting device
|
|
String across
top plates and center partition, anticipate trusses
|
|
- Storage
room sheathing using OSB
|
|
Prepare trusses
for first truss (exterior & interior)
|
|
|
- Mark 1x3
on 24" centers for truss ties
|
|
|
- Prepare
& install pic board & braces
|
|
|
- First truss
up and braced from inside
|
|
|
- Start gable
end sheathing
|
|
|
|
Essential
Main Sequence:
|
|
Simultaneous
Odd Jobs:
|
- Common trusses
lifted up onto plates via ladders, or over the side
|
|
- Brace front
door entry wall to trusses
|
|
Common truss
erection starts and proceeds non-stop
|
|
- Chalk lines
snapping 24" centers for roof (rough side up)
|
|
Small truss
(porch offset) erection must have continous alignment or plumb cut ends
|
|
- Install
attic floor 3/4" plywood
|
|
Last gable
end truss up & braced
|
|
- Hand up
roof sheathing to roof crew
|
|
Front/rear
and porch rakes up
|
|
- Fasten truss
hurricane ties with Simpson nails
|
|
Gutter boards
up both sides (caution: demo proper height via small blocks
|
|
- Truss internal
"X" bracing
|
|
Start roof
deck sheathing; bottom course snap chalk lines both sides
|
|
- Check all
framing from plans (wall alignment, window sizes, corners drywall blocking)
|
|
Cut & fit
roof sheathing stagger joints
|
|
- Remove all
internal bracing & nails
|
|
Install roof
safety planks (long 2x4's) Caution all crews about sawdust roof
|
|
- Homeowner
kick walls for quality control on sheathing
|
|
Ensure 2"
wide ridge gap at peak for birdbox building; see diagram
|
|
- Metal drip
edge installed
|
|
|
|
- Gather debris
into piles & bags or trailer; all useful materials stored; nail up door
coverings and load trucks with ladders and tools
|