----- Tuesday, August 26, 2008 -----
Shawn Out
 All Day (every day)
Electricians: 1220 Euclid plugs & switches; 605 Caldwell rough in
 All Day
Directors' Mtg. @ Floyd St.
 9:30 AM-11:00 AM (every Tuesday from 9:30 AM to 11:00 AM)
----- Wednesday, August 27, 2008 -----
Dream Machine (w/ Churchill Downs): 3119 W. Muhammad Ali siding
 All Day
Shawn Out
 All Day (every day)
Charlie's Team: 4810 Brenda framing
 All Day
Trim Crew: 1610 Beech punch & appliances
 All Day
Framers (w/ Dismas): 2023 Bank pour footer; 1510 Hemlock form flatwork; 1220 Euclid form flatwork
 All Day
Chuck's Team: 4820 Brenda insulation
 All Day
Go to MSD, get floodplain permit for 921 S. Shelby
 10:00 AM-10:30 AM
----- Thursday, August 28, 2008 -----
Richey (w/ Discernity): 3024 W. Madison move walls
 All Day
M&M: 1907 W. Chestnut paint shed, touch up
 All Day
Dream Machine: 2210 Bolling paint
 All Day
Charlie's Team (w/ Humana): 4810 Brenda windows & doors
 All Day
Framers: 1510 Hemlock pour flatwork; 1220 Euclid form flatwork
 All Day
Finish Crew: 3119 W. Muhammad Ali
 All Day
Chuck's Team (w/ Humana): 4820 Brenda drywall
 All Day
----- Friday, August 29, 2008 -----
Rose: 1322 S. 23rd framing
 All Day
Framers: 1220 Euclid pour flatwork; 3119 W. Muhammad Ali form flatwork
 All Day
Dream Machine (PSMH): 3119 W. Muhammad Ali
 All Day (every Friday)
Layout Team: 2023 Bank layout for block; 921 S. Shelby layout for dig; 530 Caldwell install gate
 All Day
Coakley (w/ NE Christian): 605 Caldwell soffit, siding, trim
 All Day (every Friday)
Construction Mtg
 9:30 AM-11:00 AM (Construction Center) (every Friday from 9:30 AM to 11:00 AM)
----- Saturday, August 30, 2008 -----
Construction Sites Closed in observance of Labor Day
 All Day