4401 North Camden Lane

  • Sponsor - Semonin Realtors in honor of Charlie Walker with matching funds provided by Holloran Trust
  • Partner Family - Joyce & John
  • Family Advocate - Charlene Kline
  • House Leader - Chuck's Team
  • Design Worksheet
  • Habitat Staff - Ron
  • Raise-the-Roof - September 13, 2008
  • Build Schedule-  Walls & ceilings painted, ready for doors & trim..

last updated on: 11/15/2008

  



20080825 - Wall Building at the Center with Zoeller

20080825 - Wall building at the center with Zoeller  20080825 - Wall building at the center with Zoeller 


20080918 - What can you do on a job site with no electrical power???

20080918 - The U of Chicago crew - Jessica & Jeremy, bending white metal  20080918  - Perfectionist at work - Donna trimming the big front windows.  20080918 - Larry the mud guy - getting the mech room ready for furnace  20080918 - Roofer Girls - Jessica & Lynn "sunbathing" while making repairs  20080918 - One of ~1000 consults in a day - need to redo the F-channel  20080918 - George, trying to kill himself in the sun filling the ditch w/ dirt - the red trash can is his "wheelbarrow"!


20081016 - Progress on the Shed & Last of the White Metal
(and BTW -  we have power at the house now!)

 


20081023 - Drywall

       

Also - Insulation Fixes


20081025 - Drywall - Day 2

     
The entire house is hung except for the bathroom and laundry/utility room!


20081107 - Saturday with volunteers from Crestwood Baptist Church

   
Gutters, starting window trim, and (almost) finishing the shed.


20081115 - Saturday
What do you do on a miserable, cold, rainy Saturday?
Work inside a toasty warm house - install doors, trim
windows, and finish most of the baseboard!